COMPLETED PROJECTS > INFRASTRUCTURE PROJECTS

14.736M İSKİ DISPLACEMENT LINE CONSTRUCTION BETWEEN TERKOS-KAĞITHANE IN THE SCOPE OF ISTANBUL NEW AIRPORT CONSTRUCTION |
PROJECT INFORMATION |
Within the scope of the contract signed with İGA Havalimanları İnşaat Adi Ortaklığı Ticari İşletmesi on 02.02.2015, the displacement of the İSKİ clean water line going from Terkos lake to Kağıthane was carried out within the airport construction boundary and 14.736m Ø2200 spiral steel pipe installation, 14.736m trench channel excavation and Back sign, 2.000.000 m³ project platform excavation, 34 suction cup structures and suction chamber construction, 20 discharge structures and evacuation chamber construction, 4 Ø2200 line valves were mechanically mounted and manufactured within the scope of the project.